| Description |
| These streets are located within the Frenchtown neighborhood and currently experience frequent flooding causing a buildup of debris and property damage. This project includes rebuilding the roadways, enclosing the roadside ditches, adding curb & gutter and constructing a sidewalk on one side of the road. |
| Type |
| I - Reconstruction of residential streets |
| |
| Preliminary Cost Estimate |
| Design |
$50,000.00 |
| Right of Way |
$90,000.00 |
| Construction |
$260,000.00 |
| Utility Relocation |
$200,000.00 |
|
| Total |
$600,000.00 |
|


 |