| Description |
| This project is a high priority within the Southside Revitalization strategy, the South Monroe Sector Plan, and the Providence Renaissance Neighborhood initiative. It includes rebuilding the roadway, enclosing ditches, adding curb & gutter, and sidewalk/bike lanes on both sides of the road. |
| Type |
| II - Reconstruction of neighborhood collector streets |
| |
| Preliminary Cost Estimate |
| Design |
$100,000.00 |
| Right of Way |
$150,000.00 |
| Construction |
$500,000.00 |
| Utility Relocation |
$100,000.00 |
|
| Total |
$850,000.00 |
|


 |