| Description |
| This project is part of the Southside Revitalization strategy, the South Monroe Sector Plan and the Providence Renaissance Neighborhood Plan. The project includes rebuilding the roadway, enclosing ditches, adding curb & gutter and a sidewalk on one side of the road. It will provide residents access to Taltran transit routes 11 & 20, and to Pineview Elementary School. |
| Type |
| I - Reconstruction of residential streets |
| |
| Preliminary Cost Estimate |
| Design |
$60,000.00 |
| Right of Way |
$60,000.00 |
| Construction |
$300,000.00 |
| Utility Relocation |
$119,000.00 |
|
| Total |
$539,000.00 |
|


 |